[Kolab-devel] [issue587] Linux'ism in upgrade procedure to BETA1
    Steffen Hansen 
    steffen at klaralvdalens-datakonsult.se
       
    Mon Jan  3 14:14:44 CET 2005
    
    
  
On Wednesday 29 December 2004 09:07, Matt Douhan wrote:
> New submission from Matt Douhan <matt at fruitsalad.org>:
>
> When upgrading to BETA 1 from an earlier version of kolab, the
> upgrade fails because a Linux specific switch is used for the cp
> command, on FBSD we do not have the -a switch to cp and hence the
> cp-ra backup will fail.
>
> Line 202 in kolab_bootstrap is the offender AFAICS
I replaced it with "cp -pR". Would that work for you?
regards
-- 
Steffen Hansen          |       Klarälvdalens Datakonsult AB
Senior Software Engineer|       http://www.klaralvdalens-datakonsult.se
                        |
                        |       Platform-independent